Commercial Notes
No. 22
9 May 2007
MANAGING CONTRACTS IN THE PUBLIC SECTOR
In Commonwealth procurement the business of managing
contracts is generally not well understood. Public accountability
obligations mean agencies are held to a higher standard
of contract management than private sector organisations.
Poor contract management in Commonwealth procurement
is an ongoing issue which is highlighted in ANAO reports
and Senate Estimates hearings.
What is contract management?
Contract management is the process through which agencies
seek to effectively manage the inherent risks of a commercial
relationship to ensure that the rights and interests of
the Commonwealth are safeguarded. In the Commonwealth context,
additional complexity is added to the commercial relationship
through the operation of Commonwealth legislation and policies
(e.g. the Financial Management and Accountability Act
1997, the Commonwealth Authorities and Companies
Act 1997, the Archives Act 1983 and the Auditor-General
Act 1997).
This note discusses issues regarding the contract management
phase of a goods or services contract under the purchaser/provider
model, as this represents the ‘standard’ form
of Commonwealth procurement. A tailored contract management
plan is required for specialised contracting models such
as strategic alliances and public private partnerships.
Contract management is influenced by the entire procurement
process but it is beyond the scope of this note to discuss
how contract management issues should be addressed throughout
the procurement cycle, specifically the pre-contract (Request
for Tender preparation), tender evaluation to contract,
and contract implementation phases. Nonetheless, the importance
of these stages to contract management cannot be underestimated,
and careful consideration, and in some cases specific advice,
is required.
A prerequisite to effective management in the contract
management phase of a procurement is that the contract1:
- properly defines the services or the scope of work
- contains appropriate risk mitigators (e.g. warranties,
indemnities, liquidated damages, financial undertakings
and performance guarantees)
- contains appropriate performance measures
- complies with Commonwealth legal and policy requirements
(e.g. privacy, confidentiality and security concerns).
If the contract is deficient in any of these respects
then potentially there will be significant inherent issues
to manage.
Effective contract management involves actively engaging
with the contractor to achieve agreed outcomes. The extent
of the engagement will depend on the contracting environment
and the scope of the risks to each party that flow from
the contract.
In addition to active engagement, the key to effective
contract management is monitoring the performance of the
contract to:
- ensure that the commitments and obligations of both
parties are met
- diligently manage identified risks to the agency
- monitor contractual events to ensure problems do not
occur
- deal with problems that do occur in a proactive manner
to limit their effect.
Poor contract management is often a major cause of disputes,
leading to dysfunctional and adversarial relationships
between the parties which may culminate in commercial litigation.
Without effective contract management, agencies may also
fail to obtain value for money through the life of the
contract.
Contract objectives should be clearly defined and appropriate
processes set in place to help monitor progress and provide
feedback to ensure that contract deliverables, including
services, are provided:
- as required
- to the agreed standard
and that inadequate standards are detected as early as
possible and promptly addressed.
The ANAO has recently published Developing and Managing
Contracts: Better Practice Guide (February 2007)
which is a useful reference tool for use by agencies
when managing contracts.
This note is intended as a summary of some of the important
contract management tasks and issues that will confront
contract managers during the life of a contract. It is
not intended to be a contract management manual. If a manager
is faced with specific contract management issues outside
their experience and expertise, then AGS recommends that
the manager seeks advice from the agency’s procurement
area and/or seeks legal advice.
Legal and policy environment
The legislative framework, within which an agency must
conduct its procurement activities, includes:
- For FMA bodies
- Financial Management and Accountability Act 1997 (FMA
Act)
- Financial Management and Accountability Regulations
1997
- Financial Management and Accountability Orders 2005
- Agency Chief Executive Instructions (CEIs), policies
and procedures
- For CAC bodies
- legislation which establishes the body
- the Corporations Act 2001 (for CAC companies)
- Commonwealth Authorities and Companies Act 1997 (CAC
Act)
- Commonwealth Authorities and Companies Regulations
1997
- Finance Minister’s (CAC Act Procurement) Directions
2004
- Public Service Act 1999 for most FMA bodies
and some CAC bodies
- Archives Act 1983
- Auditor-General Act 1997
- Commonwealth Procurement Guidelines for all
FMA bodies and most CAC bodies
- Agency Operational Instructions on, for example, Procurement
of Goods and Services.
This list is not exhaustive.
FMA agencies – Financial Management and Accountability
Act framework
The FMA Act regulates the exercise of powers by chief
executives of agencies regarding the spending of public
monies (among other things). Chief executives usually devolve
these powers by delegation or authorisation to specified
senior officers in the agency. The CEIs of each agency
provide guidance to the particular agency on the application
of aspects of the FMA Act framework. CEIs often include
instructions on topics such as ‘Approving and Authorising
Proposals to Spend Public Money’, ‘Procurement
of Property and Services’ and ‘Contract Management
and Variations’. Only a person who is designated
as an ‘approver’ of the spending of public
money under the FMA Act framework can approve spending
which is to be made under a contract. This strictly means
that only an ‘approver’ can authorise (within
their delegation) claims for payment or variations to the
contract involving expenditure.
It can therefore be helpful if contract managers are ‘approvers’.
If they are, they should be aware of the ambit of their
delegated power. If they are not, they will need to work
in close collaboration with a person who is an approver.
It is not uncommon for officers who are not ‘approvers’ (i.e.
hold no financial delegation) to be involved in routine
contract administration tasks (e.g. processing claims for
payment, reporting requirements under the contract etc.).
Australian Public Service (APS) Code of Conduct
Most public sector contract managers are APS employees
and as such must comply with the APS Code of Conduct set
out in section 13 of the Public Service Act 1999 (PS
Act). In order to comply with the code, APS employees must,
among other things:
- behave honestly and with integrity in the course of
APS employment
- act with care and diligence in the course of APS employment
- when acting in the course of APS employment, treat
everyone with respect and courtesy, and without harassment
- when acting in the course of APS employment, comply
with all applicable Australian laws. For this purpose, ‘Australian
law’ means:
- any Act (including the PS Act), or any instrument
made under an Act, or
- any law of a State or Territory, including any instrument
made under such a law
- use Commonwealth resources in a proper manner
- not provide false or misleading information in response
to a request for information that is made for official
purposes in connection with the employee’s APS
employment
- at all times behave in a way that upholds the APS
values and the integrity and good reputation of the APS.
Acting fairly and reasonably
The APS Code of Conduct and the FMA regime are consistent
with a number of judicial statements requiring the Commonwealth
to act fairly and reasonably at all times in its commercial
dealings. For example, the Federal Court referred to this
requirement in the Hughes case.2 This
essentially means that the Commonwealth may be held to
a higher standard than commercial parties.
CAC bodies – Commonwealth Authorities and Companies
Act framework
CAC authorities
The authority’s enabling legislation and the CAC
Act and associated regulations, orders and directions establish
the framework under which CAC authorities undertake procurement
activities. Powers and functions of CAC authorities are
usually vested in either the board of the body or the chief
executive, with the ability for delegations or authorisations
to be put in place to other officers of the body. In some
cases, significant contracts (including significant variations
to existing contracts) are required to be approved by the
relevant minister.
Officers of CAC authorities will need to ensure that they
have appropriate authorisation to undertake procurement
activities and contract management and are acting in accordance
with the body’s internal procedures and instructions.
The CAC Act imposes obligations on the officers and employees
of CAC bodies in relation to:
- the exercise of care and diligence
- the requirement to act in good faith
- the requirement not to use their position or information
gained through their position to gain advantage for themselves
or others or to cause detriment to the body.
CAC companies
For CAC bodies that are companies, the Corporations
Act 2001 imposes similar obligations to the CAC Act
on officers of the company in relation to good faith
obligations etc. In addition, the company’s constitution
will also establish the framework under which the company’s
business is undertaken by identifying which decisions
are to be made by shareholders (e.g. the minister) and
directors. Most companies will have specific authorisations
and procedures issued by the board or the chief executive
for company officers to undertake procurement and contract
management activities, particularly those involving spending
money.
Contract manager’s role
Complex or significant contracts often have a designated ‘contract
manager’ who is responsible for day-to-day administration
and management of the contract and a designated ‘contract
authority’ who is responsible for ‘strategic’ decision-making
under the contract (e.g. approving variations, dispute
resolution). The term ‘contract manager’ is
used generically in this note to refer to the person who:
is the primary agency representative with whom the contractor
has dealings, has legal and contractual oversight of the
contract and is generally responsible for defining the
kind of relationship to be fostered between the agency
and the contractor. This role requires the contract manager
to actively manage the working relationship between the
agency and the contractor.
This means the contract manager will also generally:
- act as an initial point of contact for the contractor
for all correspondence and legal and operational communications
under the contract
- negotiate and agree contract variations
- maintain records of all interactions with the contractor
- seek to resolve disputes (in accordance with the relevant
contract provisions)
- provide advice on purchasing and contractual issues,
as required, including liaison with other branches and
other agencies on contracting matters including policy
and procedures.
Getting to know your contract
The contract manager should be familiar with the contractual
requirements, including:
- key provisions of the contract
- timetables and deadlines for key activities
- the contractor’s commitments
- the agency’s commitments
- a list of potential risk areas.
There are generally two types of contract provisions:
background provisions and moving provisions. Background
provisions set out the parties’ agreed legal framework,
for example, the intellectual property rights of the parties
or confidentiality and privacy obligations. Moving provisions
affect the day-to-day relationship between the parties – such
as the payment and reporting requirements.
Sometimes there can be an overlap between the provisions,
for example the confidentiality provisions can require
undertakings to be provided by subcontractors as they commence
work on the project. The difference between these two types
of provisions needs to be understood in order to design
an appropriate contract management system.
Timetables and deadlines
The manager should maintain a list of tasks and commitments,
which should be updated regularly, and should include such
items as scheduled completion dates, responsible individuals,
and a description of the last action taken by each party
in regard to each commitment/responsibility. This list
should be checked against the contract for the purpose
of monitoring and confirming the completion of tasks. For
this to be effective, it relies on the contractor’s
commitments and the agency’s commitments being properly
defined in the contract.
Potential risk areas
The contract manager should also understand the risk allocation
mechanisms in the contract. By definition, a contract is
a risk allocation mechanism between the agency and the
contractor. All contracts, regardless of their size or
type, will encounter in their operation some form of risk
that may adversely impact on the achievement of their objectives.
The specific risk allocation mechanisms in the contract
should reflect the risk assessment conducted at the beginning
of the procurement process. Major procurements often have
a specific risk management plan.
The risk assessment should be updated throughout the life
of the contract to address changes in circumstances and
associated risks with the performance and management of
the contract. Standard risk mitigators are:
- provisions for the reduction and/or the deferral of
fees for failure to perform, which tend to be quite common
in service contracts
- an indemnity clause (An indemnity is a promise
to reimburse the loss suffered by the indemnified party
where it has arisen as a result of an event covered
by the indemnity.)
- provisions limiting the agency’s (or the contractor’s)
liability
- clauses for the provision of performance guarantees (A
performance guarantee is a promise by a third party
to either perform work or pay money or both in the
event the contractor defaults.)
- liquidated damages (LD) clauses (LD clauses should
be a genuine estimate of loss that the agency would
suffer if the contractor breaches its obligations.
If the contractor breaches its obligations under a
liquidated damages clause it is required to pay the
agency the amount specified in the clause as compensation
for the agency’s loss.)
- insurance requirements (The contract should require
the contractor to insure for the risks it takes on
under the contract. Standard insurance categories for
contractors are: public liability, professional indemnity
and workers’ compensation. Specialised insurance
(such as product liability) may be specified depending
on the nature of the goods or services. For most Commonwealth
agencies, insurance arrangements are with Comcover
and Comcare for employees.)
- warranties (A warranty is a promise whereby one
party provides certain assurances to another party.)
- rights of termination for default (Under the general
law a party to a contract may terminate the contract
and seek damages from the other party where the other
party has defaulted in a way that goes to the ‘root
of the contract’ or is a ‘fundamental breach’.
Generally a termination clause is exercised where a
party is unable, or no longer willing to perform its
obligations under the contract.)
- clauses which allocate responsibility to one party
to either deal with, or pay for, particular contingencies
that may arise (e.g. rectification clauses, clauses making
one party responsible for particular costs that may arise
during the project, or clauses providing for an adjustment
to fees in the event that certain contingencies arise,
such as changes in the law).
In terms of ‘knowing your contract’ the use
of flow charts or tables to break down internal processes
and the requirements of the contract can be useful educative
and management tools. They are commonly used to break down
a variety of processes under the contract, including:
- dispute resolution processes
- performance management regimes
- payment regimes
- processes for contract change proposals.
Below is an example of a flow chart that delineates the
dispute resolution process under a significant and complex
services contract.

Relationship management
This is a key role for the contract manager. After contract
signature, the contractor will be sensitive to indications
as to how the contract manager intends to work with them.
The contractor will most likely respond to the contract
manager’s approach with a similar approach on their
side. Therefore, adopting a strict ‘manage to the
contract’ approach will probably produce a similar
approach from the contractor.
If the contract manager demonstrates a more flexible,
outcomes focused (rather than process focused) approach,
the contractor is likely to be more flexible. The challenge
for a contract manager is to implement an approach that
combines the benefits of flexibility and a focus on the
business outcomes, with the administrative rigour required
to manage risk and satisfy the agency’s and the contract
manager’s accountabilities.
While the legal requirements of the contract are determinative
of the proper course of conduct in contract management,
the exercise of skill and judgment is often required to
effectively protect the agency’s interests. It is
important to manage and not to seek to control the contractor.
Equally, it is important not to be ‘captured’ or
controlled by the contractor. Contract managers should
not fall into the trap of abdicating decision-making responsibilities
and deferring completely to the judgment of the contractor
for direction.
A strategic relationship with the contractor is also important.
Although there is a formal contractual relationship, the
parties need to recognise their mutual dependence and mutual
interest in developing a cooperative relationship. The
relationship is more likely to be a successful one if:
- there is shared qualitative understanding of the task
to be achieved and the objectives of the contractual
relationship
- if the expectations of both parties are realistic
- there are effective mechanisms for clear, open and
effective communication to permit the contractor to accommodate
the agency’s specific needs.
Managers must provide guidance in setting responsibilities
for the contractor, managing the performance of the contractor
in respect of those responsibilities, and facilitating
the delivery of the services by the contractor. Contract
managers should be alert to opportunities to assist the
contractor. This will also include managing client or stakeholder
expectations of the contractor’s performance, including:
- establishing realistic expectations of the contractor’s
capabilities and desired outcomes
- establishing the limits of the contractor’s
responsibilities
- educating clients or stakeholders about how the contract
will fit into the agency’s business strategy
- ensuring that the agency complies with any obligations
it has under the contract
- developing processes in relation to service delivery
and interaction with the contractor.
Communication and contract amendments
Effective contract management requires the agency (i.e.
the contract manager) to establish and maintain clear and
effective lines of communication and reporting procedures
with the contractor, including mechanisms to address performance
issues and resolve disputes. Systematic contacts and formal
communication procedures can ensure that a continuous dialogue
is maintained with the contractor so that the contractor
is aware of developments within and outside the agency,
particularly changes that might impact on the scope of
work and service delivery.
A crucial part of managing the flow of information between
the contractor and the agency involves understanding the
implications of such communication. As illustrated in the
decision of the Federal Court of Australia in the GEC Marconi
case3 which is analysed in AGS Commercial
Notes No. 8 (17 January 2004), a contract can be varied
by conduct (including waiver and/or estoppel) or oral representation.
In Australia there are no statutory requirements concerning
the form of contract variations except for certain limited
classes of transactions, such as dealings in land. A contract
will usually have a standard clause providing at a minimum,
that the contract can only be amended by agreement in writing.
Notwithstanding this writing requirement, a contract can
be amended at common law by:
- waiver (the renunciation of some legal right)
- oral representation
- acting inconsistently with the terms of the contract
(‘estoppel’, the prevention of a party from
asserting in legal proceedings a position contrary to
that established by other means).
It is important for contract managers to assess the implications
of their communications by considering whether the verbal
directions they intend to give the contractor accord with
the terms of the contract. If they do not, the contract
manager may unintentionally create a contract variation.
Where contract managers are dealing with what may be an
out-of-scope requirement, they should minimise the risk
of unintentionally varying the contract by making it clear
in any communications (including oral and email communications)
they have with the contractor, that discussions are subject
to agreement being reached in writing and signed by both
parties.
Monitoring performance
A significant obligation of the contract manager involves
monitoring performance in accordance with the contractual
performance measurement system and making timely decisions.
There are a number of steps that will facilitate effective
performance monitoring:
- Ensure good internal corporate knowledge of the performance
measurement system. (Ideally performance indicators and
measures should be integrated with both parties’ management,
accounting and financial systems. Intrusive reporting
will be counter-productive and costly, placing administrative
burdens on both parties.)
- Ensure good internal project planning, particularly
if the contract is being performed in stages or as an
ongoing service.
- Hold timely meetings with the contractor regarding
day-to-day operations and performance, including problem
and risk management.
- Promptly follow up on the cause of performance problems
and remedial efforts undertaken by the contractor to
prevent the recurrence of problems.
- Periodically review and, where necessary, vary the
contract requirements in order to reflect changing business
priorities, lessons learned from experiences in the relationship,
and improved performance capabilities.
Record management – audit trail
Record management provides information critical to competent
contract management, including performance monitoring,
decision making and dispute resolution. Sound contract
management and administration relies on the maintenance
of a complete audit trail to ensure decisions or processes
can be reviewed and to demonstrate accountability to program
managers (and ultimately to Parliament). The extent of
the documentation required largely depends on the circumstances
and likely consequences but is also dependent on satisfying
the legislative requirements regarding Commonwealth record
keeping (under the Archives Act 1983, the FMA Act
and the CAC Act).
In contract management, routine matters can quickly and
easily escalate to become non-routine and/or expensive
disputes. Having access to all relevant correspondence
and records of events can be vital in settling a dispute
before it escalates. It can also be crucial in any litigation
proceedings as it is likely that the agency will be called
upon to produce a wide range of documents relating to the
procurement process and management of the contract. Accurate
record keeping will also ensure the agency retains valuable
corporate knowledge and expertise gained in respect of
contract management. Corporate memory of key issues, lessons
learned, the strengths and weaknesses of the contract and
the parties, and possible improvements are a valuable asset
which can be retained and disseminated through documentation
of contract procedures and the maintenance of good contract
records.
Contract management skills
The skills and experience of the people assigned to contract
management functions is an important consideration. The
ideal mix of skills will change as the procurement moves
through its life cycle. Nevertheless, relevant skills and
experience include:
- an understanding of the project’s needs
- experience in managing projects
- good negotiation and interpersonal skills
- an understanding of government accounting and financial
principles, including the ability to control budgets
and expenditures
- knowledge and understanding of Commonwealth procurement
processes and the legal framework in which the agency
is required to manage projects (e.g. FMA Act or the CAC
Act, Auditor-General’s Act 1997)
- knowledge and some understanding of relevant aspects
of commercial law, including the principles of contract
law
- an understanding of risk management techniques and
contingency planning
- the ability to work effectively as a member of a team
- well developed analytical skills
- the ability to exercise sound judgment
- the ability to work reliably under pressure and prioritise
competing demands
- technical expertise sufficient to provide the agency
with correct advice on the contractor’s performance.
Common legal issues
In our experience, contract management is often poor (with
commensurate contractual and legal implications) in the
following key areas:
Work commences before execution
The parties have acted as if a contract is in place when
the contract has not yet been signed or is still being
negotiated and there are later disputes about whether
or not there is a contract, and if so, the scope of
the contract, its duration and conditions.
Incomplete records
There are deficient or incomplete documentary records
of contract management decisions (such as directions
given to the contractor) or the outcomes of significant
interactions with the contractor (whether each party
has a common understanding of how to proceed). Where
the agency and the contractor have a difference of
view on a particular issue, it is important for the
agency to ensure that it documents its position with
the contractor and does not leave correspondence from
the contractor asserting a particular position unanswered – this
may otherwise give rise to an implication that the
agency accepts the contractor’s position.
Variations not in the appropriate form
This follows and is linked to the previous area, particularly
the requirement that any amendment to the contract
be in writing and signed by both parties. Instances
of a contract being amended orally (in meetings or
over the telephone), by conduct (especially failure
to act consistently with the contract), by email exchanges
or by informal ‘letter agreements’ kept
in ‘bottom drawers’ (i.e. not on file)
are relatively common.
Variations or waivers not properly authorised
A complex contract will often specify that only the ‘contract
authority’, not the designated ‘contract
manager’, can formally approve variations or waivers.
Breach of insurance provisions
Over time, particularly in longer term contracts, the
contractor may not renew its insurance policies or
the coverage or terms of those policies may change
in such a way as to reduce the protection that they
afford. As a consequence, it is not unusual for contractors
to be in breach of the insurance provisions of a contract
unless the agency has an annual process for checking
the extent to which the contractor maintains the required
insurance policies on an ongoing basis.
Payment not properly authorised
Decisions to approve payments are not made by an officer
with the appropriate level of financial delegation.
GST under the contract not managed effectively
Most contracts contain provisions dealing with GST. However,
in addition to having the right GST clause in the contract,
it is often necessary to manage particular GST considerations,
particularly for contracts that are cost plus or allow
for reimbursement of expenses. A common issue with
these contracts is for a contractor to claim reimbursement
for the full amount of an expense, including GST paid,
where it is also able to claim an input tax credit
for that expense – this in effect gives the contractor
a windfall.
Plans not followed up
Contracts often provide for various matters to be dealt
with under plans that are developed and approved post
signature (e.g. risk management plans or transition
out plans) and are required to be implemented. In many
cases, agencies do not follow up on these plans and
when the time comes to implement the plan (e.g. on
transition out) the contractor has no plan and is uncooperative.
Deferral or reduction of fees not enforced when
appropriate
Contracts often contain a clause allowing the agency
to defer or reduce payments if the services are not being
performed by the contractor to the agency’s satisfaction.
It is not unusual for an agency to continue to make payments
to the contractor despite poor performance. In addition
to raising questions about the extent to which such payments
are an ‘efficient and effective’ use of public
money under the FMA Act, in some circumstances, payments
to the contractor can waive the agency’s right
to remedies under the contract and at law.
Difficulties in identifying confidential information
Contracts typically contain confidentiality clauses which
allow parties to identify material which is to be regarded
as commercial-in-confidence for a specified period,
subject to specific agency accountability processes.
Over time, where there are many interactions between
contractor and contract manager with a mixture of confidential
and non-confidential material, clearly identifying
which material is covered by the confidentiality clause
can become difficult.
Extension of the contract not managed effectively
Whether to re-tender or extend the contract is often
considered too late. Where a contract is extended,
often this gives rise to a new procurement and requires
consideration of the Commonwealth Procurement Guidelines,
and for FMA agencies, FMA Regulation 9 approval and
where applicable FMA Reg 10 authorisation. Similarly,
contracts are often extended without a corresponding
extension to the terms of any risk mitigation mechanisms
under the original contract, such as unconditional
financial undertakings or performance guarantees.
This list is not exhaustive. Contract managers will need
to assess the extent to which of the areas outlined above
may arise in their contracts and develop an appropriate
contract management system.
When to seek legal advice
A contract manager cannot be expected to deal with every
possible situation that arises in relation to a contract.
An important skill in contract management is recognising
when to seek legal advice. As a contract manager has the
ability to affect the agency’s rights through their
actions it is important to be pro-active throughout the
life of the contract and seek legal assistance before issues
escalate.
Situations where it would be prudent to consider obtaining
legal advice include where:
- the contract manager believes that the contractor
may be in default under the contract
- the agency is considering terminating or reducing
the contract’s scope for convenience
- it is necessary to change the nature or scope of the
contract
- the agency is in dispute with the contractor about
any material matter or the contract manager considers
that dispute is likely
- a conflict of interest arises
- a security breach or a breach of confidentiality occurs.
Again this list is not exhaustive. Contract managers will
need to exercise their judgment if other contract management
issues arise that could require legal advice.
This note has been prepared by Clare Derix and Henry
Addison with the assistance of Kathryn Graham, Senior
General Counsel and Cathy Reid, Senior Executive Lawyer.
Clare Derix joined AGS’s Commercial Group in
Canberra in 2002 after spending two years working in
private practice in the commercial and financial services
area. Clare has drafted a broad range of contracts for
clients and regularly advises on how best to manage and
administer contracts. She has extensive experience in
providing legal and probity advice in relation to acquisition
and market-testing projects, tender documentation and
the legal and Commonwealth policy re-quirements with
respect to procurement.
Henry Addison joined AGS’s Commercial Group in
Canberra in 1999. Prior to that he had a varied commercial
law career, including private practice in London and
Los Angeles. Henry has extensive experience in contract
administration and management, and a comprehensive knowledge
of Commonwealth requirements and policies in relation
to pro-curement, competitive tendering and contracting
and the use of whole-of-government arrangements. He also
has broad experience as probity adviser on tender documentation
and contract negotiations.
Notes
- ‘Contract’ here is used generically to
refer to all relevant contractual documentation, not
just the terms and conditions of contract (e.g. the Schedules
of the contract such as the Statement of Work or Functional
Performance Specification, the Performance Measurement
System, the Project Plan etc.). The term also includes
documents that are incorporated by reference, such as
Australian Standards or industry codes of practice.
- Hughes Aircraft Systems International v Air Services
Australia (1997) 146 ALR 1.
- GEC Marconi Systems Pty Limited v BHP Information
Technology Pty Limited (2003) 201 ALR 55.
Ten key principles of contract management
The following principles apply to any contracting
situation and should be borne in mind for successful
contract management:
-
Be proactive in contract management – do
not allow minor problems to become major ones.
-
Communicate regularly and effectively with
the contractor – work for a strategic relationship
with the contractor.
-
Understand the contract and what is required
of all parties – clearly define roles and
responsibilities.
-
Identify the particular risks faced by the
contract and monitor events to limit their effect – actively
manage risks.
-
Ensure the contractual obligations of both
the agency and the contractor are fulfilled in
accordance with the contractual requirements.
-
Behave ethically and honestly at all times,
and require the same standards of the contractor.
-
Regularly review the requirements of the contract
and the contractor’s performance.
-
Seek professional advice when warranted – advice
from the agency’s procurement area and
legal advice, should be sought where required.
-
Be reasonable and fair when dealing with the
contractor but enforce the contractual terms
and conditions when appropriate – there
are limits to conciliation.
-
Ensure variations to the contract are justified,
provide value for money and do not diminish the
agency’s requirements or interests.
|
Reference material for contract managers
Commonwealth Procurement Guidelines, Department of
Finance and Administration, January 2005 (Financial
Management Guidance No. 1)
Guidance on Confidentiality of Contractors’ Commercial
Information, Department of Finance and Administration,
February 2003 (Financial Management Guidance No. 3)
Guidance on the Listing of Contract Details on the
Internet, Department of Finance and Administration,
January 2004 (Financial Management Guidance No. 8)
Guidance on Complying with Legislation and Policy in
Procurement, Department of Finance and Administration,
January 2005 (Financial Management Guidance No. 10)
Guidance on Identifying Consultancies for Annual Reporting
Purposes, Department of Finance and Administration,
July 2004 (Financial Management Guidance No. 12)
Guidance on the Mandatory Procurement Procedures,
Department of Finance and Administration, January 2005
(Financial Management Guidance No. 13)
Guidance on Ethics and Probity in Government Procurement,
Department of Finance and Administration, January 2005
(Financial Management Guidance No. 14)
Guidance on Procurement Publishing Obligations,
Department of Finance and Administration, January 2005
(Financial Management Guidance No. 15)
Guidance on the Gateway Review Process – A Project
Assurance Methodology for the Australian Government,
Department of Finance and Administration, August 2006
(Financial Management Guidance No. 20)
Developing and Managing Contracts – Getting the
Right Outcome, Paying the Right Price: Better Practice
Guide, Australian National Audit Office, February 2007
‘Commercialising intellectual property’ and ‘Commercialisation
and confidentiality’, AGS Commercial Notes No.
18, 24 February 2006
‘Indemnities in Commonwealth contracting’,
AGS Legal Briefing No. 79, 26 July 2006
AGS contacts
AGS has national teams of lawyers specialising in contract
development and management, including managing contractual
disputes. For further information on the article in this
issue, or on other contract management issues please contact
John Scala (development and management) or Simon Daley
(disputes), the authors, or any of the lawyers listed below.
National
|
John Scala
Simon Daley
|
03 9242 1321
02 9581 7490*
|
Canberra
|
Garth Cooke
Andrew Whiteside
Andrew Berger
|
02 6253 7010
02 6253 7137
02 6253 7405*
|
Sydney
|
John Berg
Simon Daley
|
02 9581 7624
02 9581 7490*
|
Melbourne
|
Paul Lang
Susan Pryde
|
03 9242 1322
03 9242 1426*
|
Brisbane
|
Richard Silver
Barry Cosgrove
|
07 3360 5700
07 3360 5647*
|
Perth
|
Scott Slater
Jonathan Jacobson
|
08 9268 1144
08 9268 1135*
|
Adelaide/Darwin
|
Andrew Schatz
|
08 8205 4201
|
Hobart
|
Peter Bowen
|
03 6210 2104
|
* For enquiries regarding disputes.
The material in these notes is provided to AGS clients
for general information only and should not be relied
upon for the purpose of a particular matter. Please
contact AGS before any action or decision is taken
on the basis of any of the material in these notes. © AGS
All rights reserved
© Australian
Government Solicitor